South Pars Desalination Pipeline Project

Omid Pars Consortium is proud to announce that with the support of research and development and innovation, it has been able for the first time to operate a GRVE deep-sea transmission line.

Location: Assaluyeh Dock Yadgar Imam

Description:

GRVE pipes are made of fibers and have very high mechanical strength and high corrosion resistance to chemical and alkaline fluids and are quick to install.

Drilling and dredging method:

Omid Pars Consortium has used the latest machinery and equipment for sea bed dredging by Tug Floating & Brag.

Installation Method:

After assembling the Spool 48 m long, each spool attaches to the A-frame and is transported by crane to the installation site at sea and placed in the desired location in the canal. The divers go deep into the sea after installation and close the bolts in place.

Backfill Operation:

Once installation is complete, it is the turn of the backfill operation that must be performed with great care to protect the pipe.